Hither Green Station May 2026
Hither Green Station May 2026
During a 72-hour railway possession, teams installed four bridge spans in just 10 hours as part of Network Rail’s Access for All programme. Using 500-tonne and 750-tonne mobile cranes, the new footbridge was lifted into place, connecting all platforms and bringing step-free access to the station for the first time.
Location
Hither Green Station, London
Plant used
500-tonne and 750-tonne mobile cranes




Abnormal load and complex heavy lift engineering
Abnormal load and complex heavy lift engineering
From a port to a sand bunker – an abnormal load and complex heavy lifting project for TGE Gas Engineering
Location: Bristol
Load type
Earth covered tanks
Weight
104 tonnes

Airbridge Lift at Southampton Docks
Airbridge Lift at Southampton Docks
Multiple technical lifts with two 150-tonne Liebherr LTM1150-5.3 cranes
Location: Southampton Docks
LOAD TYPE
Tunnels and structures
Weight
5-47 tonnes
Equipment
Two Liebherr LTM1150 cranes

Little Chayne Wind Farm in Rye
Little Chayne Wind Farm in Rye
Wind rotator and gearbox – changing main drive shaft bearing.
Client
WTE
Duration
5 Days
Plant used
Ltm1650 and Ltm1230




Ash Road Bridge
Ash Road Bridge
Bridge project improved traffic, air quality, safety, and housing opportunities
Location: Surrey
YEAR
2024
Plant used
750T

Aylesbury Stocklake McDonalds
Aylesbury Stocklake McDonalds
Full contract lift inclusive of plant and machinery movement
Location: Aylesbury
Duration
04/08/2025 – 06/08/2025
Plant used
LTM1500 – T6Y3 – 135tCW
Lift type
Full contract lift inclusive of plant and machinery movements

Oxford Street – Road Closure and Lift
Oxford Street – Road Closure and Lift
KL delivered a fully managed contract lift under full road‑closure conditions to install a diverse package of plant for a major construction project. The operation required extensive planning, multi‑agency coordination, and precision execution across a full weekend possession.
Client
McLaren
Year
October 2025
Plant used
LTM1300
56t counterweight
TN 31.5 luffing jib
60t rigging crane
Lift type
Contract lift




Baggott & Sons – Portacabin Move
Baggott & Sons – Portacabin Move
A fast-turnaround commercial lift involving the relocation and installation of a portacabin using dual cranes. A practical example of our support for construction and commercial clients needing precision placement in tight timeframes.
Location
Romsey
Lift type
Full Contract Lift
Client
Baggott & Sons
Sector
Construction



Royal Mint Tower Crane Erection
Royal Mint Tower Crane Erection
Supplied our Liebherr LTM1650-8.1 700 tonne capacity mobile crane to erect a tower crane in London
Location
London
Plant used
Liebherr LTM1650-8.1


Tower Crane Dismantle at Trafalgar Way, London
Tower Crane Dismantle at Trafalgar Way, London
King Lifting was appointed by LTC to undertake the dismantle of a Jost JTL 168.8 luffing jib tower crane positioned on a rooftop steel grillage at Trafalgar Way, London, adjacent to Canary Wharf. The roof level was approximately 113.0m above road level.
Client
LTC
Duration
3 days
Plant used
LTM 1650‑8.1
LTM 1090‑4.2




Bishop’s Lydeard – Bridge Installation
Bishop’s Lydeard – Bridge Installation
A civil infrastructure project delivering a new bridge to support access to a water treatment facility and surrounding farmland. A clean, efficient contract lift demonstrating our capability in essential infrastructure upgrades.
Location
Somerset
Lift type
Full Contract Lift
Client
Envolve Infrastructure
Sector
Infrastructure



Building Bridges for Briton Fabricators
Building Bridges for Briton Fabricators
Iconic bridge restored for Briton Fabricators
Location: Birmingham
LOAD TYPE
U Decks
Weight
110 tonnes x 2
Equipment
800-tonne Liebherr LTM1750-9.1

Iron Action Substation
Iron Action Substation
Lifting 8 battlers and 2 AC skids per day and then moving the crane ready for the next day. Batteries weigh 41t and ac skids weigh 36t. 11 setups total. LTM1230 used with various ballast to accommodate the tight site conditions, travelled with full 72t of ballast each time.
Client
High voltage grid services
Plant used
LTM1230
Lift type
Lifting x76 41t batteries and 19 AC skids weight 36t using various modular beams. 11 setups total.


Exeter University
Exeter University
Lifting 54 Algeco cabins into place for the new offices for Bouygues construction at Exeter University
Client
Algeco
Location
Exeter University
Plant used
90t
Lift type
Contract lift


Challenging and time-constrained lifts for Midland Metro Alliance
Challenging and time-constrained lifts for Midland Metro Alliance
Successful technical lift for Midland Metro Alliance
Location: West Midlands
Load type
Switch & Crossing Points
Weight
9.9 tonnes
Equipment
LIEBHERR LTM1750-9.1
Specification

WW2 ‘Whale’ Bridge Recovery
WW2 ‘Whale’ Bridge Recovery
A “rare surviving” relic of the D-Day landings could be relocated to the entrance of an army port. Associated British Ports (ABP) wanted to move a flexible roadway section of a WW2 Mulberry Harbour called Whale, which was in Town Quay, Southampton.
Client
MMMB Engineering Ltd
Year
October 2025
Plant used
LTM1500




Glastonbury CPA lift
Glastonbury CPA lift
Lift and lower petrol station forecourt roof
Location
Glastonbury
Lift type
CPA
Client
Contract Lift UK
Sector
Construction



Installation of temporary pedestrian bridge
Installation of temporary pedestrian bridge
The installation of a temporary pedestrian bridge spanning the River Thames at the heart of the iconic Reading Festival
Location: Reading
Lift type
21t Intermediate Lift
Plant used
Terex AC350 with 116t c/w
Duration
½ day rigging, 1 night lifting, ½ day derigging

Bishops Gate PMM and Heavy Cranes
Bishops Gate PMM and Heavy Cranes
KL’s Heavy Crane Division was commissioned to deliver a series of complex rooftop lifts for two key clients—MCS and PiP—requiring the coordinated deployment of one of the most capable cranes in our fleet: the LTM1650‑8.1 configured on T5N, with 155 tonnes of counterweight and a 70‑metre luffing jib.
Year
October 2025
Duration
3 days
Plant used
LTM1650-8.1



Lifting a tunnel boring machine from 35 metres under London’s streets
Lifting a tunnel boring machine from 35 metres under London’s streets
Going underground – a lifting and moving project for the National Grid and Hochtief-Murphy Joint Venture
Location: London
View Case Study
Overhead aerial wire installation for the Commonwealth Games
Overhead aerial wire installation for the Commonwealth Games
King Lifting assist with logistics at Commonwealth Games
Location: Birmingham
View Case Study
Precision roof replacement for major city stadium
Precision roof replacement for major city stadium
Unmatchable stadium lifting support for the Principality Stadium in Cardiff
Location: Cardiff
View Case Study
Transport bridge Winchester
Transport bridge Winchester
Remove old bridge beams and transport to customers compound
Client
Carney construction
Location
Winchester
Plant used
LTM 650
Lift type
Bridgewater beam removal


University Station, Birmingham
University Station, Birmingham
King Lifting completed rail project safely, on time, within budget, despite challenges
Location: University Station, Birmingham
YEAR
June 2021 – November 2021
Value
£1 million
Plant used
500te Liebherr LTM1500-8.1
300te Liebherr LTM1300-6.2
200te Liebherr LTM1200-5.1